Chat with us, powered by LiveChat 3.2 Case Study: Nightingale Project Gantt Chart - EssayAbode

3.2 Case Study: Nightingale Project Gantt Chart

3.2 Case Study: Nightingale Project Gantt Chart

To complete this assignment, you can use the Nightingale Gantt Chart Template attached here and the Rubric to help you.

I will share more files later. 

Case Study Rubric

Case Study Rubric

Criteria

Ratings

Pts

This criterion is linked to a Learning Outcome(Individual + Group) Deliverables address all activity requirements.

25 pts

Exemplary

Deliverables address all activity requirements.

17 pts

Proficient

Deliverables address most activity requirements.

14 pts

Marginal

Deliverables address some activity requirements.

11 pts

Weak

Deliverables address little activity requirements.

0 pts

No Credit

Missing

25 pts

This criterion is linked to a Learning Outcome(Individual) Content of deliverables demonstrates clear comprehension and/or skill application.

25 pts

Exemplary

Content of deliverables demonstrates clear comprehension and/or skilled application of all activity concepts.

17 pts

Proficient

Content of deliverables demonstrates clear comprehension and/or skilled application of most activity concepts.

14 pts

Marginal

Content of deliverables demonstrates clear comprehension and/or skilled application of some activity concepts.

11 pts

Weak

Content of deliverables provides little comprehension and/or skilled application of activity concepts.

0 pts

No Credit

Missing

25 pts

This criterion is linked to a Learning Outcome(Individual + Group) Responses include strong support.

25 pts

Exemplary

All responses include strong support for decisions such as logical, technically sound rationale or credible research.

17 pts

Proficient

Most responses include support for decisions such as logical, technically sound rationale or credible research.

14 pts

Marginal

Some responses include strong support for decisions such as logical, technically sound rationale or credible research.

11 pts

Weak

Only a few responses include strong support for decisions such as logical, technically sound rationale or credible research.

0 pts

No Credit

Missing

25 pts

This criterion is linked to a Learning Outcome(Individual + Group) Professional communication was applied.

25 pts

Exemplary

All communication is clear, professional, and respectful.

17 pts

Proficient

Most communication is clear, professional, and respectful.

14 pts

Marginal

Some communication is clear, professional, and respectful.

11 pts

Weak

Only a little of the communication is clear, professional, and respectful.

0 pts

No Credit

Missing

25 pts

Total Points: 100

,

Project Network Diagram

PMT472L 3.2 CASE STUDY: NIGHTINGALE PROJECT – PART A
Original Project Network Diagram
Construct a project network diagram for the stadium project, displaying activity ID, duration, earliest start, earliest finish, latest start, latest finish, and slack for each activity. Assume that the final activity in the diagram will have the same earliest finish and latest finish. NOTE: Copy-paste and fill in the 3×3 cell set to create building blocks for your project network diagram.
ES ID EF 0 1 10
SL SL ? ?
LS DUR LF ? 10 ?

Gantt Chart Schedule

Related Tags

AcademicAPAAssignmentBusinessCapstoneCollegeConclusionCourseDayDiscussionDouble SpacedEssayEnglishFinanceGeneralGraduateHistoryInformationJustifyLiteratureManagementMarketMastersMathMinimumMLANursingOrganizationalOutlinePagesPaperPresentationQuestionsQuestionnaireReferenceResponseResponseSchoolSubjectSlidesSourcesStudentSupportTimes New RomanTitleTopicsWordWriteWriting

PMT472L 3.2 CASE STUDY: NIGHTINGALE PROJECT – PART A
Original Gantt Chart Schedule
Develop the Gantt chart schedule for the project to determine its estimated completion date.
Activity Duration (days) Start Date Finish Date Predecessor(s) 1/3/17 1/4/17 1/5/17 1/6/17 1/9/17 1/10/17 1/11/17 1/12/17 1/13/17 1/16/17 1/17/17 1/18/17 1/19/17 1/20/17 1/23/17 1/24/17 1/25/17 1/26/17 1/27/17 1/30/17 1/31/17 2/1/17 2/2/17 2/3/17 2/6/17 2/7/17 2/8/17 2/9/17 2/10/17 2/13/17 2/14/17 2/15/17 2/16/17 2/17/17 2/20/17 2/21/17 2/22/17 2/23/17 2/24/17 2/27/17 2/28/17 3/1/17 3/2/17 3/3/17 3/6/17 3/7/17 3/8/17 3/9/17 3/10/17 3/13/17 3/14/17 3/15/17 3/16/17 3/17/17 3/20/17 3/21/17 3/22/17 3/23/17 3/24/17 3/27/17 3/28/17 3/29/17 3/30/17 3/31/17 4/3/17 4/4/17 4/5/17 4/6/17 4/7/17 4/10/17 4/11/17 4/12/17 4/13/17 4/14/17 4/17/17 4/18/17 4/19/17 4/20/17 4/21/17 4/24/17 4/25/17 4/26/17 4/27/17 4/28/17 5/1/17 5/2/17 5/3/17 5/4/17 5/5/17 5/8/17 5/9/17 5/10/17 5/11/17 5/12/17 5/15/17 5/16/17 5/17/17 5/18/17 5/19/17 5/22/17 5/23/17 5/24/17 5/25/17 5/26/17 5/30/17 5/31/17 6/1/17 6/2/17 6/5/17 6/6/17 6/7/17 6/8/17 6/9/17 6/12/17 6/13/17 6/14/17 6/15/17 6/16/17 6/19/17 6/20/17 6/21/17 6/22/17 6/23/17 6/26/17 6/27/17 6/28/17 6/29/17 6/30/17 7/3/17 7/5/17 7/6/17 7/7/17 7/10/17 7/11/17 7/12/17 7/13/17 7/14/17 7/17/17 7/18/17 7/19/17 7/20/17 7/21/17 7/24/17 7/25/17 7/26/17 7/27/17 7/28/17 7/31/17 8/1/17 8/2/17 8/3/17 8/4/17 8/7/17 8/8/17 8/9/17 8/10/17 8/11/17 8/14/17 8/15/17 8/16/17 8/17/17 8/18/17 8/21/17 8/22/17 8/23/17 8/24/17 8/25/17 8/28/17 8/29/17 8/30/17 8/31/17 9/1/17 9/5/17 9/6/17 9/7/17 9/8/17 9/11/17 9/12/17 9/13/17 9/14/17 9/15/17 9/18/17 9/19/17 9/20/17 9/21/17 9/22/17 9/25/17 9/26/17 9/27/17 9/28/17 9/29/17 10/2/17 10/3/17 10/4/17 10/5/17 10/6/17 10/9/17 10/10/17 10/11/17 10/12/17 10/13/17 10/16/17 10/17/17 10/18/17 10/19/17 10/20/17 10/23/17 10/24/17 10/25/17 10/26/17 10/27/17 10/30/17 10/31/17 11/1/17 11/2/17 11/3/17 11/6/17 11/7/17 11/8/17 11/9/17 11/10/17 11/13/17 11/14/17 11/15/17 11/16/17 11/17/17 11/20/17 11/21/17 11/22/17 11/24/17 11/27/17 11/28/17 11/29/17 11/30/17 12/1/17 12/4/17 12/5/17 12/6/17 12/7/17 12/8/17 12/11/17 12/12/17 12/13/17 12/14/17 12/15/17 12/18/17 12/19/17 12/20/17 12/21/17 12/22/17 12/27/17 12/28/17 12/29/17
Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed Thu Fri Mon Tue Wed