Q1 – If 1,490 compacted cubic yards of in-place soil is required for a project, how many loads of import will be re

Q1 – If 1,490 compacted cubic yards of in-place soil is required for a project, how many loads of import will be required? The import material has a swell of 14 percent and shrinkage of 95 percent. The trucks can haul 12 loose cubic yards.

Q2 – Determine the amount of excavation needed for the continuous footings shown below. A two-foot working distance is required and the excavation will be sloped 1:1.75 (1.75 vertical feet for every horizontal foot). Also, determine the amount of backfill needed for the continuous footing and foundation in compacted cubic yards.

Q3 – An asphalt paving crew is used to pave a 500-foot by 300-foot parking lot. The parking lot will be paved in 12-foot-wide strips running the long (500-foot) direction. The machine paves 11 lineal feet of 12-foot-wide parking lot per minute. A single lift of asphalt will be used on the parking lot. After completing a pass, it takes the crew 10 minutes to turn the paving machine around and get ready for the next pass. The crew consists of a foreperson, six operators, and a laborer. Using a system efficiency of 50 minutes per hour, determine the number of labor hours required to place 1 lineal foot of parking lot 12 feet wide.

Related Tags

Academic APA Assignment Business Capstone College Conclusion Course Day Discussion Double Spaced Essay English Finance General Graduate History Information Justify Literature Management Market Masters Math Minimum MLA Nursing Organizational Outline Pages Paper Presentation Questions Questionnaire Reference Response Response School Subject Slides Sources Student Support Times New Roman Title Topics Word Write Writing