Chat with us, powered by LiveChat Process Management Prepare a flowchart of one of the following: Choosing which anniversary date to go on with your significant other Which specific product to choose Oth - EssayAbode

Process Management Prepare a flowchart of one of the following: Choosing which anniversary date to go on with your significant other Which specific product to choose Oth

Look at the attachment. There is two different projects and both need to be completed according to the guidelines provided.

Extra Credit: Process Management – up 25 points possible.

Choose between one of the two options below. A tutorial is provided.

Option A:

Using the FREE online software provided at: www.gliffy.com (see link)

Prepare a flowchart of one of the following:

1) Choosing which anniversary date to go on with your significant other

2) Which specific product to choose

3) Other as approved by instructor

Must contain at least 5 processes and 2 decisions points and 1 database. It may contain more.

Worth up to 20 points.

Option B:

Using the FREE online software provided at: www.gliffy.com (see link)

Create a process model using swim lanes (2 or 3) and prepare a simple process model using flowchart notation for the same items above.

Must contain at least 2 swim lanes, 5 processes and 2 decisions points and 1 database. It may contain more.

Worth up to 25 points.

This is an individual effort!

ITEM

Points

Comments

Problem statement & Memo

5

Processes (min 5)

5

Decisions (min 2)

5

Database

5

Swimlanes

5

TOTAL

25

,

Project management Lab Page 1

Project management Lab Page 3

USE THIS PROJECT – NOT ONE OF YOUR OWN CREATION!

Computer Installation

You are the Information Systems Project Manager for ABC, Incorporated. To improve the administration of XYZ, Inc. your company has been contracted to install a new computer system in XYZ’s corporate headquarters and in all five of their district offices. A development team consisting of the PM, SA, SO, and Sr. HT have determined that the following list of activities is key to completing the project.

Task

Task Name

Duration

Personnel

Percent of Assigned Time

1

Prepare preliminary systems design and obtain approval

20

Project Mgr

Systems Analyst

SysOps

Sr. Hardware Tech

25

75

25

25

2

Prepare detailed systems design

20

Project Mgr

Systems Analyst

SysOps

Sr. Hardware Tech

50

50

25

25

3

Select equipment

15

Project Mgr

Systems Analyst

SysOps

Sr. Hardware Tech

25

25

75

75

4

Order and receive equipment

30

Project Manager

Contracting Agent

Equipment

10

20

5

Prepare sites for installation

5

1 Sr. Hardware Tech

2 Hardware Techs

100

100

6

Install equipment

30

1 Sr. Hardware Tech

2 Hardware Techs

100

100

7

Conduct total systems test

10

SysOps

100

8

Develop user’s manual

30

Tech writer

Editor

Sysops

Sr. Hardware Tech

100

25

5

10

9

Train users on system

10

SysOps

Sr. Hardware Tech

100

100

Resource Sheet

Personnel

Contract Billing Per Hour ($)

Project Manager

80

Systems Analyst

55

SysOps

75

Sr. Hardware Tech

65

Hardware Tech

58

Contracting Agent

45

Tech Writer

45

Editor

50

Predecessors: The Project team has determined that 1 must precede 2 must precede 3 must precede 4. 3 must precede 5 must precede 6 must precede 7. 4 & 7 must precede 8 must precede 9.

Assume a work week is 40 hours, Monday through Friday. Overtime rate is 1 ½ times the contract cost. Holiday rate is 2 times the contract cost. However, XYZ, Inc. has not authorized any use of overtime or holiday rates. The start date for the project is June 15.

Make sure you fill out RESOURCES SHEET and assign them! You only need to complete Resource Name and Standard Rate. This is found under Task, then click the down arrow by Gantt Chart.

CREATE a Gantt chart, Network Diagram, Resource Sheet of this Project. The Network Diagram is created as you are creating the Gantt Chart.

Assign resources as listed in the tables above to the Gantt chart. This is done on the Gantt Chart. Highlight which task you want to assign the resources to, then right click and choose Assign Resources. Choose the right person and enter the percent as shown on the table on page 1.

What are the different paths and what is the critical path and how long is it? Look at the Network Diagram to determine the different paths and calculate how long each path is and determine the Critical Path.

If the cost of equipment is $350,000, what is the overall contracted cost of the project? Add this to the cost of all the different employees for the total cost of the project. To find this information, go to Project, Project Information then click Statistics.

In this exercise, students will use Project Management Software to:

· Calculate the Critical Path.

· Predict overall cost of a project.

Rubric:

ITEM

Points

Comments

Correct Use of PM Software

Activities Entered (5 for list; 10 for duration)

15

Predecessors Entered

10

Resources entered (including overtime): 10 for Resource sheet; 15 for Assigning Resources

25

Paths & Critical Path & Number of days

25

Overall Cost of the Project

25

TOTAL

100

100 Points Total

PAGE

100 Points Total

Related Tags

Academic APA Assignment Business Capstone College Conclusion Course Day Discussion Double Spaced Essay English Finance General Graduate History Information Justify Literature Management Market Masters Math Minimum MLA Nursing Organizational Outline Pages Paper Presentation Questions Questionnaire Reference Response Response School Subject Slides Sources Student Support Times New Roman Title Topics Word Write Writing