20 Sep Given: A foundation plan with a footing schedule. A sketch of the F1.0 cast-in place concrete spread footing showin
Given:
A foundation plan with a footing schedule.
A sketch of the F1.0 cast-in place concrete spread footing showing rebar.
Dimensions: as shown on footing schedule and sketch.
Materials:
3000 psi concrete.
#5 rebar as shown, 1.043 LB/LF.
Wood formwork
Installed prices include material and installation.
Concrete $217.17 / CY
Rebar $1.69 / LB
Formwork $9.47 / SFCA
Calculate the volume of concrete in cubic yards (CY) for each footing.
Calculate the price of concrete for each footing.
Calculate the weight of rebar in pounds (LB) for each footing.
Calculate the price of rebar for each footing.
Calculate the area of formwork in square feet of contact area (SFCA) for each footing.Calculate the price of formwork for each footing.
Calculate the total price of each footing to an accuracy of two decimal places.
Calculate the total price of all F1.0 footings to an accuracy of two decimal places.