10 Jul Using the following information: Build a network diagram Identify the early start, early finish, late start late finish for each activity Identify the critical pa
Using the following information:
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H
Activity Predecessor Duration in Days
A Start 3
B Start 6
c A, B 12
D B 5
E D 4
F C 6
G E,F 8
H E 7
I H 3