Question

Question 1.1.Which is a key benefit of the Control Cost process? 

Provides the means to recognize variance from the plan in order to take corrective action
Approves changes to the budget
Assures the project will not overrun the budget
Makes changes to the Project Management Plan
Question 2.2.Actual cost is: 

the authorized budget assigned to scheduled work.
the realized cost for the work performed.
the activity amount before any reserves are included.
a measure of the work performed expressed in terms of the budget authorized for that work.

Question 3.3.There is (are) _________ way(s) to calculate the EAC. 

four

two

three

one

Question 4.4.What should be used if EVM is not being used? 

Actual costs
Planned costs

Budgeted costs

Analysis of the cost baseline against actual costs for the work performed

Question 5.5.If earned value (EV) = 450, actual cost (AC) = 500, and planned value (PV) = 425, what is cost performance index (CPI)? 

1.11

0.85

0.9

1.18

    Related Tags

    Academic APA Assignment Business Capstone College Conclusion Course Day Discussion Double Spaced Essay English Finance General Graduate History Information Justify Literature Management Market Masters Math Minimum MLA Nursing Organizational Outline Pages Paper Presentation Questions Questionnaire Reference Response Response School Subject Slides Sources Student Support Times New Roman Title Topics Word Write Writing